Case Studies 2008
  • Requirement: Network cutover to new Cisco router and VLAN port map
    View Case Study
  • Requirement: Bring new functionality to the end user PC troubleshooting bench
    View Case Study
  • Requirement: Completion of PCI network standardization
    View Case Study
  • Requirement: Upgrade backup appliance to current specification standards
    View Case Study
Case Studies 2007

Project Overview

  • Customer Format: Retail Store Chain
  • Project Name: Confidential
  • Completion Time Frame: 120 days
  • Number of Locations: 921
  • Customer Requirement: Cutover to new Cisco router and VLAN port map. Segragated wireless network traffic from point of sale traffic for PCI compliance.
  • R&R Methodology Advantage: R&R employs an experienced team of Managed Services professionals. We incorporate teams within our national logistics coverage. This consists of our own warehouse, driver/technician and vehicles. Our ability to plan, resource and manage the Turn-key execution of emergency customer projects provides cost savings and eliminates handoff and multi-vendor coordination costs.

Project Scope

On Site Activities:
  • Remove 4 existing Cisco Access Points
  • Run new home run cable for 5th Access Point
  • Install 5 new Cisco Access Points
  • Clean up production troubleshooting bench with cable management
  • Install approximately 3 new Cisco switches in troubleshooting bench
  • Tone 4 home run cables for troubleshooting bench to communications closet
  • Test all new cables with cable tester for cross talk and continuity
  • Cut Over to new network

Summary

The project was completed on time within the strict PCI required deadline.